TRAFFIC ALERT UPDATE
Johnson County Gateway #jocogateway
FOR IMMEDIATE RELEASE
May 20, 2016
News Contact: Kimberly Qualls, (785) 640-9340 or [email protected]
I-35 & I-435 Interchange Weekend-Long & Overnight Full Road Closures
WEEKEND-LONG FULL ROAD CLOSURE of eastbound and westbound I-435 as follows:
8 p.m. Friday, May 20 to 5 a.m. Monday, May 23 | Eastbound I-435 ALL LANES at I-35 CLOSED. |
10 p.m. Friday, May 20 to 5 a.m. Monday, May 23 | Westbound I-435 ALL LANES at I-35 CLOSED. |
Advance message boards will alert drivers to the weekend-long full road closures. Marked detours will be provided as follows. See marked detour map below.
WEEKEND VARYING CLOSURES for northbound and southbound I-35 are as follows:
Northbound I-35:
9 p.m. Friday, May 20 to 10 a.m. Saturday, May 21 | Northbound I-35 ALL LANES at I-435 CLOSED. |
10 a.m. to 8 p.m. Saturday, May 21 | Northbound I-35 TWO RIGHT LANES at I-435 CLOSED. Only one through lane OPEN to traffic. |
8 p.m. Saturday, May 21 to 6 a.m. Sunday, May 22 | Northbound I-35 ONE LEFT LANE at I-435 CLOSED. Two through lanes OPEN to traffic. |
6 a.m. Sunday, May 22 to 5 a.m. Monday, May 23 | Northbound I-35 TWO RIGHT LANES at I-435 CLOSED. Only one through lane OPEN to traffic. |
Southbound I-35:
8 p.m. Friday, May 20 to 5 a.m. Monday, May 23 | Southbound I-35 TWO LEFT LANES from 75th Street to I-435 CLOSED. Only one through lane OPEN to traffic. |
Advance message boards will alert drivers to the overnight full road closures. Northbound I-35 marked detour via eastbound I-435 to northbound U.S. 69 to northbound I-35. See marked detour map below.
Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.
The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.
Overall #JoCoGateway Phase Two Project work is scheduled to be completed in December 2016. (KDOT Project #435-46 KA-1002-06)