The old bridge over Santa Fe Trail Drive demolition is nearly complete, down to the piers.PermalinkGallery

Santa Fe Bridge Demo Work

2015, December 2015

Santa Fe Bridge Demo Work2015-12-22T13:30:25+00:00Noise wall panels are installed near I-435 and Pflumm Road.PermalinkGallery

Pflumm Wall Perspective

2015, December 2015

Pflumm Wall PerspectiveRobyn Arthur2015-12-22T13:27:44+00:00Here is a rare view of the edge brackets supporting the crews on the walkway above.PermalinkGallery

I-35/I-435 Flyover Perspective

2015, December 2015

I-35/I-435 Flyover PerspectiveRobyn Arthur2015-12-22T13:25:22+00:00Rebar cages are installed over the deck panels for the new EB I-435 to NB I-35 two-lane flyover.PermalinkGallery

Flyover Rebar

2015, December 2015

Flyover RebarRobyn Arthur2015-12-22T13:26:48+00:00Crews finish the details for street sign installation on Lackman Road.PermalinkGallery

Lackman Sign Installation

2015, December 2015

Lackman Sign InstallationRobyn Arthur2015-12-19T20:25:55+00:00Crews work to finish the deck forms for the new flyover.PermalinkGallery

WB I-435 at NB I-35 Deck Work

2015, December 2015

WB I-435 at NB I-35 Deck WorkRobyn Arthur2015-12-19T20:25:12+00:00One of the boxes which forms the larger box culvert drain is installed under the east end of 95th Street at I-35.PermalinkGallery

I-35 at 95th Street Box Culvert Installation

2015, December 2015

I-35 at 95th Street Box Culvert InstallationRobyn Arthur2015-12-19T20:23:26+00:00A sign truss goes up at SB I-435 and K-10.PermalinkGallery

Sign Truss Installaton at SB I-435 and K-10

2015, December 2015

Sign Truss Installaton at SB I-435 and K-10Robyn Arthur2015-12-10T15:44:19+00:00Crews pump out water and build forms for the drain basin area off K-10 and I-435.PermalinkGallery

K-10 and I-435 Drain Basin Work

2015, December 2015

K-10 and I-435 Drain Basin WorkRobyn Arthur2015-12-10T15:32:02+00:00Crews readjust and replace damaged barrier throughout the project limits.PermalinkGallery

Barrier Work at I-435 and Lackman

2015, December 2015

Barrier Work at I-435 and LackmanRobyn Arthur2015-12-10T15:28:14+00:00Box culvert installation is reviewed at NB I-35 and the 95th Street ramp.PermalinkGallery

I-35 at 95th Street

2015, December 2015

I-35 at 95th StreetRobyn Arthur2015-12-10T15:26:17+00:00A view from above the new Lackman Road/I-435 interchange.PermalinkGallery

Lackman at I-435

2015, December 2015

Lackman at I-435Robyn Arthur2015-12-04T11:47:17+00:00WB I-435 right lanes near Quivira were milled and asphalt recycled on 12.1.15.PermalinkGallery

I-435 Mill Work and Haul Trucks

2015, December 2015

I-435 Mill Work and Haul TrucksRobyn Arthur2015-12-04T11:46:36+00:00Crews grade the slope along the approach to the flyover bridge, while others finish installing the stay-in-place steel decking.PermalinkGallery

I-435 Approach Work

2015, December 2015

I-435 Approach WorkRobyn Arthur2015-12-04T11:45:44+00:00Carpenters finish installing temporary handrail along a bridge above Santa Fe Trail Drive.PermalinkGallery

Carpenters above Santa Fe

2015, December 2015

Carpenters above Santa FeRobyn Arthur2015-12-04T11:44:55+00:00Crews continue paving work along the approach to the WB I-435 to SB I-35 flyover ramp.PermalinkGallery

WB I-435 to SB I-35 Ramp Construction

2015, November 2015

WB I-435 to SB I-35 Ramp ConstructionRobyn Arthur2015-11-25T15:19:57+00:00The wall panels at Pflumm continue to be assembled.PermalinkGallery

Pflumm Wall Work

2015, November 2015

Pflumm Wall WorkRobyn Arthur2015-11-25T15:19:06+00:00Crews pick up cones left to the side of the road following overnight lane closures.PermalinkGallery

EB K-10 Traffic Cones

2015, November 2015

EB K-10 Traffic ConesRobyn Arthur2015-11-25T15:18:04+00:00Crews pick barrier along EB I-435 near Pflumm.PermalinkGallery

I-435 Barrier Removal

2015, November 2015

I-435 Barrier RemovalRobyn Arthur2015-11-25T15:17:08+00:00Crews work fast to finish the abutments along Santa Fe Trail Drive. Girders will be placed here soon.PermalinkGallery

Santa Fe Abutment

2015, November 2015

Santa Fe AbutmentRobyn Arthur2015-11-21T07:54:55+00:00Crews install metal decking which will go under the concrete slab. This I-435 flyover ramp bridge is over I-35.PermalinkGallery

I-435 Deck Work

2015, November 2015

I-435 Deck WorkRobyn Arthur2015-11-21T07:54:13+00:00An ironworker cuts stay-in-place metal decking sheets to go over the bridge deck.PermalinkGallery

I-435 Flyover Bridge Deck Welding

2015, November 2015

I-435 Flyover Bridge Deck WeldingRobyn Arthur2015-11-21T07:53:23+00:00Handrails and plywood platforms are a fall-protection method that help crews continue work on the bridge deck safely.PermalinkGallery

I-435 Flyover Handrail Installation

2015, November 2015

I-435 Flyover Handrail InstallationRobyn Arthur2015-11-21T07:52:19+00:00Permalink

EB I-435 near Lackman

2015, Aerial, November 2015

EB I-435 near LackmanRobyn Arthur2015-11-15T20:44:47+00:00Lenexa Drive opened at Pflumm Road on October 29, 2015. Thanks to Dave Vanecek for this photo.PermalinkGallery

Lenexa Drive Now Open at Pflumm

2015, November 2015

Lenexa Drive Now Open at PflummRobyn Arthur2015-11-07T14:07:07+00:00The Lackman ramp to I-35 opened on Friday, October 30. Photo credit: David VanecekPermalinkGallery

Lackman Ramp Open

2015, November 2015

Lackman Ramp OpenRobyn Arthur2015-11-07T14:06:06+00:00The slight slope and angle of the ramps can be a challenge for the GOMACO paver at times. Photo credit: Steve ManleyPermalinkGallery

I-435 Flyover Deck Pour

2015, November 2015

I-435 Flyover Deck PourRobyn Arthur2015-11-07T14:04:21+00:00Early morning hours capture one of the last few paving jobs on the Gateway project. Photo credit: Steve ManleyPermalinkGallery

I-435 Flyover Deck Pour

2015, November 2015

I-435 Flyover Deck PourRobyn Arthur2015-11-07T14:03:19+00:00Pflumm Road under I-35 is set to open Saturday, October 24th - weather permitting.PermalinkGallery

Pflumm Road under I-35

2015, October 2015

Pflumm Road under I-35Robyn Arthur2015-10-23T15:15:36+00:00A carpenter sets forms up for rebar tie-ins across I-35.PermalinkGallery

I-35 Road Construction

2015, October 2015

I-35 Road ConstructionRobyn Arthur2015-10-23T15:14:42+00:00An ironworker checks coated rebar in the media between NB and SB I-35 lanes.PermalinkGallery

I-35 Road Work

2015, October 2015

I-35 Road WorkRobyn Arthur2015-10-23T15:13:51+00:00Ramp construction continues on the east interchange ramps. This deck will receive concrete in the coming weeks.PermalinkGallery

East Interchange Flyover Ramp

2015, October 2015

East Interchange Flyover RampRobyn Arthur2015-10-23T15:08:42+00:00Grading work continues in preparation for the Lackman on-ramp paving.PermalinkGallery

Lackman Ramp Grading

2015, October 2015

Lackman Ramp GradingRobyn Arthur2015-10-15T09:04:21+00:00Crews prepare the grade between barrier for the eastbound collector-distributor road and the eastbound Lackman off-ramp.PermalinkGallery

EB Lackman Ramp Grading

2015, October 2015

EB Lackman Ramp GradingRobyn Arthur2015-10-15T09:03:43+00:00Ironworkers tie rebar for the pending barrier pour, which will take place along this bridge Lackman Road for the new eastbound collector-distributor road.PermalinkGallery

Collector-Distributor Bridge Work

2015, October 2015

Collector-Distributor Bridge WorkRobyn Arthur2015-10-15T09:02:41+00:00A snapshot of the work occurring simultaneously on I-435, Lackman Road Ramps and the new eastbound collector-distributor road.PermalinkGallery

I-435/Lackman Ramp/EB Collector-Distributor Look

2015, October 2015

I-435/Lackman Ramp/EB Collector-Distributor LookRobyn Arthur2015-10-15T09:01:50+00:00Pflumm Road work continues as utility depths are confirmed prior to additional excavation.PermalinkGallery

Pflumm Road Utility Work

2015, October 2015

Pflumm Road Utility WorkRobyn Arthur2015-10-12T09:37:37+00:00Crews continue work on one of the I-435 bridges over K-10.PermalinkGallery

I-435 Bridge Work

2015, October 2015

I-435 Bridge WorkRobyn Arthur2015-10-12T09:36:45+00:00Crews are working hard to complete the eastbound collector-distributor road near I-435 and Lackman.PermalinkGallery

Eastbound C-D Road Work

2015, October 2015

Eastbound C-D Road WorkRobyn Arthur2015-10-12T09:35:50+00:00Crews get into the grate and drain installation along the eastbound collector-distributor road - opening soon.PermalinkGallery

Eastbound C-D Drain Installation

2015, October 2015

Eastbound C-D Drain InstallationRobyn Arthur2015-10-12T09:34:33+00:00Damaged guardrail is replaced along I-35.PermalinkGallery

I-35 Guardrail Replacement

2015, September 2015

I-35 Guardrail ReplacementRobyn Arthur2015-10-01T13:53:56+00:00Stay In Place metal decking is visible under crew boots. SIP decking keeps flyover bridges lighter, without sacrificing strength.PermalinkGallery

Stay In Place Decking on NB I-35 Flyover

2015, September 2015

Stay In Place Decking on NB I-35 FlyoverRobyn Arthur2015-10-01T13:52:10+00:00Ironworkers tie rebar across the deck for the new NB I-35 to WB I-435 flyover ramp.PermalinkGallery

NB I-35 to WB I-435 Flyover Deck Work

2015, September 2015

NB I-35 to WB I-435 Flyover Deck WorkRobyn Arthur2015-10-01T13:51:16+00:00A view of new pavement along the EB C-D road.PermalinkGallery

EB Collector-Distributor Road

2015, September 2015

EB Collector-Distributor RoadRobyn Arthur2015-09-26T14:18:37+00:00Construction of the MSE wall continues along Santa Fe Trail Drive.PermalinkGallery

Santa Fe MSE Wall

2015, September 2015

Santa Fe MSE WallRobyn Arthur2015-09-26T14:17:31+00:00Aerial View of K-10 Basin WorkPermalinkGallery

Aerial View of K-10 Drain Basin Work

2015, Aerial, September 2015

Aerial View of K-10 Drain Basin WorkRobyn Arthur2015-09-26T14:16:35+00:00Lackman Road work continues as a new median is added between 105th and 101st Streets. Lane reductions will be in place through mid-October.PermalinkGallery

Lackman Road Asphalt Work

2015, September 2015

Lackman Road Asphalt WorkRobyn Arthur2015-09-26T14:15:26+00:00Aerial View of K-10 Ramps at Renner BoulevardPermalinkGallery

K-10 Ramps at Renner Blvd

2015, September 2015

K-10 Ramps at Renner BlvdRobyn Arthur2015-09-21T15:20:13+00:00Girder and bridge work over Lackman Road.PermalinkGallery

Lackman Girder Work

2015, September 2015

Lackman Girder WorkRobyn Arthur2015-09-21T15:19:27+00:00Aerial photo of the widening work on NB I-35 over Pflumm Road.PermalinkGallery

NB I-35 at Pflumm Road

2015, September 2015

NB I-35 at Pflumm RoadRobyn Arthur2015-09-21T15:17:49+00:00Renner Road is now open to traffic, with few traffic controls in place until final items are finished.PermalinkGallery

Renner Road Now Open

2015, September 2015

Renner Road Now OpenRobyn Arthur2015-09-14T14:38:03+00:00A water line is installed under I-35, and under Pflumm Road.PermalinkGallery

Pflumm Road Utility Work

2015, September 2015

Pflumm Road Utility WorkRobyn Arthur2015-09-14T14:37:12+00:00Rebar is inspected following an overnight girder set over Lackman Road.PermalinkGallery

K-10 Bridge Work Over Lackman Road

2015, September 2015

K-10 Bridge Work Over Lackman RoadRobyn Arthur2015-09-14T14:36:13+00:00New lengths of fiber were installed to replace old fiber along Lackman Road.PermalinkGallery

New Fiber Along Lackman Road

2015, September 2015

New Fiber Along Lackman RoadRobyn Arthur2015-09-14T14:34:49+00:00Concrete girders are placed near the I-435 ramp to K-10.PermalinkGallery

K-10 Ramp and Concrete Girder Set

2015, Aerial, August 2015

K-10 Ramp and Concrete Girder SetRobyn Arthur2015-09-03T13:12:51+00:00Deck panels are placed on a flyover ramp above K-10.PermalinkGallery

K-10 Bridge Work

2015, August 2015

K-10 Bridge WorkRobyn Arthur2015-09-03T13:11:56+00:00Paving for one of the new Lackman ramps is underway.PermalinkGallery

Lackman Road Ramp

2015, August 2015

Lackman Road RampRobyn Arthur2015-09-03T13:11:12+00:00The pending girder set will start the final work for this two-lane flyover ramp connection.PermalinkGallery

Girder Gap To Be Filled

2015, August 2015

Girder Gap To Be FilledRobyn Arthur2015-09-03T13:10:14+00:00A view of the I-35 weekend girder set at I-435.PermalinkGallery

I-35 Girder Set – Aerial Daytime View

2015, Aerial, August 2015

I-35 Girder Set – Aerial Daytime ViewRobyn Arthur2015-09-03T13:09:13+00:00An ironworker bolts the girder into place on I-35 at I-435 in early Sunday morning fog.PermalinkGallery

Ironworker works in fog at I-35

2015, August 2015

Ironworker works in fog at I-35Robyn Arthur2015-09-03T13:07:52+00:00Crews pave a connection between the new Pflumm Road bridge over I-35 road.PermalinkGallery

I-35 above Pflumm-Bridge Paving

2015, August 2015

I-35 above Pflumm-Bridge PavingRobyn Arthur2015-09-03T13:06:31+00:00Nighttime aerial view of the girder set on 8/29/15 of the I-35 girders at I-435.PermalinkGallery

I-35 Girders Set at I-435

2015, Aerial, August 2015

I-35 Girders Set at I-435Robyn Arthur2015-09-03T13:04:40+00:00Lackman Road at I-435 is changing. Girders will be set shortly across the road for the new C-D roadway. The Lackman ramp to EB I-435 closed this week for additional work through November 1.PermalinkGallery

Lackman Road Work

2015, August 2015

Lackman Road WorkRobyn Arthur2015-08-24T10:25:39+00:00Piers and forms are visible along Santa Fe Trail Drive near I-435 as road work extends.PermalinkGallery

Santa Fe Formwork

2015, August 2015

Santa Fe FormworkRobyn Arthur2015-08-24T10:24:20+00:00Paving work is taking place for the new C-D road along EB K-10.PermalinkGallery

EB C-D Road Paving

2015, August 2015

EB C-D Road PavingRobyn Arthur2015-08-24T10:23:14+00:00This aerial view shows some of the interstate traffic lanes in new configurations as bridge work continues at I-435 and I-35. Photo by Jason Clarke.PermalinkGallery

WB I-435 at I-35

2015, Aerial, August 2015

WB I-435 at I-35Robyn Arthur2015-08-24T10:21:51+00:00Ironworkers cut the girders to help the demo work for the old ramp bridge from EB K-10 to NB I-435.PermalinkGallery

K-10 Bridge Demo – Girder Cut

2015, August 2015

K-10 Bridge Demo – Girder CutRobyn Arthur2015-08-21T13:44:08+00:00Aerial View of K-10 Ramp Demolition. Look for the video of this demo work on the jocogateway.com video page.PermalinkGallery

Aerial View of K-10 Ramp Demolition

2015, Aerial, August 2015

Aerial View of K-10 Ramp DemolitionRobyn Arthur2015-08-21T13:43:24+00:00Paving work to widen I-435 between Pflumm Rd. and I-35 takes place in the middle of the interstate.PermalinkGallery

Paving Crew at I-435

2015, August 2015

Paving Crew at I-435Robyn Arthur2015-08-21T13:42:37+00:00Ironworkers inspect the girders set overnight in August for the new two-lane flyover ramps.PermalinkGallery

Overnight Girder Set at I-435 and I-35

2015, August 2015

Overnight Girder Set at I-435 and I-35Robyn Arthur2015-08-21T13:41:52+00:00Crews continue to work quickly on the Lackman interchange and new ramps to get past the rain and meet deadlines.PermalinkGallery

Lackman Road Wall Work

2015, August 2015

Lackman Road Wall WorkRobyn Arthur2015-08-07T18:12:59+00:00New ramps from EB K-10 to Renner and Renner to WB K-10 will open soon!PermalinkGallery

Renner Ramps

2015, August 2015

Renner RampsRobyn Arthur2015-08-07T18:12:14+00:00An ironworker examines the pins for the deck work following the girder set at Pflumm Road and I-35.PermalinkGallery

Pflumm Bridge Ironworker

2015, August 2015

Pflumm Bridge IronworkerRobyn Arthur2015-08-07T18:11:22+00:00Work at I-35 and Lenexa Drive, I-35 and I-435, and the traffic shift all begin to show some of the scope of work for this project.PermalinkGallery

I-35 Southbound Perspective

2015, August 2015

I-35 Southbound PerspectiveRobyn Arthur2015-08-07T18:09:58+00:00Grading work continues throughout the project during these dry days of summer.PermalinkGallery

Grading Work

2015, July 2015

Grading WorkRobyn Arthur2015-07-31T16:52:21+00:00The new diverging diamond interchange at Ridgeview Road and K-10 at night.PermalinkGallery

Ridgeview DDI at Night

2015, Aerial, July 2015

Ridgeview DDI at NightRobyn Arthur2015-07-31T16:50:58+00:00A bucket loader empties into another dump truck during cut and fill work along I-35.PermalinkGallery

Fill Work

2015, July 2015

Fill WorkRobyn Arthur2015-07-31T16:49:28+00:00The new, four-lane roadway of College Boulevard and Ridgeview is clearly lit with the new halogen lights.PermalinkGallery

Nighttime Aerial View of College Blvd.

2015, Aerial, July 2015

Nighttime Aerial View of College Blvd.Robyn Arthur2015-07-31T16:47:51+00:00Workers inspect the pavement cuts for the new collector-distributor road near EB K-10.PermalinkGallery

K-10 and C-D Road Check

2015, July 2015

K-10 and C-D Road CheckRobyn Arthur2015-07-24T16:57:24+00:00An ironworker welds spots to reinforce the falsework for the pending girder set at I-435 and I-35.PermalinkGallery

Ironworker Welding Falsework

2015, July 2015

Ironworker Welding FalseworkRobyn Arthur2015-07-24T16:57:55+00:00An aerial view of the weathered girders set at I-35 during the recent full weekend closure of the interstate.PermalinkGallery

Aerial View of Girder Set

2015, Aerial, July 2015

Aerial View of Girder SetRobyn Arthur2015-07-24T16:58:27+00:00Operators stop to check the block at the I-435 and I-35 interchange. A girder set will close the eastbound lanes of I-435 overnight.PermalinkGallery

Crane Check at I-435

2015, July 2015

Crane Check at I-435Robyn Arthur2015-07-24T16:53:45+00:00The eastbound C-D Road and K-10 lanes are visible in the background, along with the new Olathe Convention Center. JoCo Project progress takes place throughout this photo.PermalinkGallery

A Look at K-10

2015, July 2015

A Look at K-10Robyn Arthur2015-07-16T13:28:55+00:00A drainage crew trying to beat the heat modified their hardhats with cardboard for this job. Temperatures topped out over 100 on the heat index.PermalinkGallery

Renner Blvd. Drainage Work

2015, July 2015

Renner Blvd. Drainage WorkRobyn Arthur2015-07-16T13:28:21+00:00July temperatures keep the heat on this paving crew. Good thing someone is trucking in Sub Zero.PermalinkGallery

Hot Pavement Patch Work

2015, July 2015

Hot Pavement Patch WorkRobyn Arthur2015-07-16T13:27:26+00:00This is an aerial view of the new eastbound collector-distributor road construction off EB K-10 to NB I-435, courtesy of Jason Clarke.PermalinkGallery

Eastbound C-D Road Construction – Aerial View

2015, July 2015

Eastbound C-D Road Construction – Aerial ViewRobyn Arthur2015-07-16T13:10:13+00:00The new weathered steel girders are in place at WB I-435 and NB I-35. The slight curve shows the flow of the two-lane flyover ramp these girders will support.PermalinkGallery

WB I-435 at NB I-35

2015, July 2015

WB I-435 at NB I-35Robyn Arthur2015-07-13T15:30:50+00:00Electrical workers run line for the light poles and signals at the Ridgeview Road bridge over K-10. This is one of the final steps toward a complete interchange.PermalinkGallery

Ridgeview Electrical Work

2015, July 2015

Ridgeview Electrical WorkRobyn Arthur2015-07-13T15:29:51+00:00This iron falsework will help hold the girders during the next steel girder set at I-435 and I-35.PermalinkGallery

I-435 at I-35 Flyover Falsework

2015, July 2015

I-435 at I-35 Flyover FalseworkRobyn Arthur2015-07-13T15:15:08+00:00Preparation for an upcoming 10-day traffic shift to reduce EB K-10 to one lane takes planning. Crews cover signs, while paving continues for the new collector-distributor road in the distance.PermalinkGallery

EB K-10 and new C-D Road

2015, July 2015

EB K-10 and new C-D RoadRobyn Arthur2015-07-13T15:10:08+00:00Striping crews work quickly overnight to mark the new interchange at Ridgeview Road and K-10.PermalinkGallery

Striping on Ridgeview Road Overnight

2015, June 2015

Striping on Ridgeview Road OvernightRobyn Arthur2015-07-02T14:38:59+00:00The diverging diamond interchange at Ridgeview Road and K-10 now has traffic signals installed and brick work complete in the medians.PermalinkGallery

Ridgeview Lighting

2015, June 2015

Ridgeview LightingRobyn Arthur2015-07-02T14:37:53+00:00Overnight on Saturday, June 27, weathered steel girders were set into place for one of the new flyover ramps under construction at I-435 and I-35.PermalinkGallery

Steel Girder Set at I-435 and I-35

2015, June 2015

Steel Girder Set at I-435 and I-35Robyn Arthur2015-07-02T14:36:46+00:00The collector-distributor road is nearly complete for eastbound traffic near K-10.PermalinkGallery

EB C-D Road

2015, June 2015

EB C-D RoadRobyn Arthur2015-07-02T14:35:53+00:00Trucks remove fill dirt and debris from the pavement removal and grade reconstruction at Renner Road and K-10 interchanges.PermalinkGallery

Renner Road Work

2015, June 2015

Renner Road WorkRobyn Arthur2015-06-27T11:19:22+00:00Deck panels are placed between the new concrete girders over Pflumm Road. This bridge deck will be part of the new collector-distributor road along I-435.PermalinkGallery

Deck Panel Set over Pflumm Road

2015, June 2015

Deck Panel Set over Pflumm RoadRobyn Arthur2015-06-27T11:17:31+00:00A collector-distributor road along K-10 will lighten interstate traffic levels through this corridor.PermalinkGallery

K-10 and Collector-Distributor Roadways

2015, June 2015

K-10 and Collector-Distributor RoadwaysRobyn Arthur2015-06-27T11:15:44+00:00Girders over I-435 at I-35 were set overnight on June 22 and 23rd. A full weekend interstate closure will be needed to set the remaining girders in this area.PermalinkGallery

I-435 Girder Set

2015, June 2015

I-435 Girder SetRobyn Arthur2015-06-27T11:13:08+00:00Trucks haul rock and dirt fill to stabilize the wall near the BNSF tracks off Santa Fe Trail Drive.PermalinkGallery

MSE Wall Fill Near Santa Fe Trail Drive

2015, June 2015

MSE Wall Fill Near Santa Fe Trail DriveRobyn Arthur2015-06-27T09:45:23+00:00Crews pick barrier in advance of the traffic shift near K-10 at Ridgeview Road.PermalinkGallery

K-10 Barrier Moves

2015, June 2015

K-10 Barrier MovesRobyn Arthur2015-06-27T09:44:08+00:00