alertJohnson County Gateway Phase 2 Construction is now complete. Be aware of additional lane closures as other construction projects begin.

update

/Tag:update
­

Marshall Drive & 95th Street Scheduled to Open Saturday, May 7

#95thStI35DDI < > #jocogateway

TRAFFIC ALERT

FOR IMMEDIATE RELEASE  

May 4, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.orgImage_95thStWestsideupcoming_May-June_2016-05-04-01

 

Marshall Drive& 95th Street

PHASE A TRAFFIC SHIFT UPDATE: Marshall Drive at 95th Street on the west side of the 95th Street and I-35 Interchange is scheduled to OPEN to traffic by 8 a.m. this Saturday, May 7, 2016, weather permitting. The new Marshall Drive underpass and two adjacent single-lane roundabouts will open allowing traffic to travel north and south on Marshall Drive separated from 95th Street, which is a major change from what drivers are used to. In addition, Marshall Drive to westbound 95th Street and eastbound 95th Street to Marshall Drive will open to traffic as well. See the detailed map above for this Phase A traffic shift configuration that will be in place through late June 2016, weather permitting.

Here’s what this means for drivers: Drivers will now utilize two new single-lane roundabouts on Marshall Drive to access 95th Street. For drivers who are not familiar with roundabouts, the Kansas Department of Transportation has a website page at this link:  http://www.ksdot.org/Roundabouts/ dedicated to roundabouts that will help you better understand how to navigate through them. Included on this page, you will find a video link: http://www.ksdot.org/Roundabouts/resources.asp that will show drivers how to safely navigate through a roundabout.

Drivers will now be able to access area businesses, including Costco, O’Reilly Auto Parts and Hoe’s Oriental Market, among others, on the west side of the interchange much easier with the opening of Marshall Drive at 95th Street.

>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>>

UPCOMING THIS SUMMER! See the two aerial maps below for the upcoming Phase B Traffic Configuration that will take place in Late June – Mid-August 2016, and a look at the Final Traffic Configuration that will take place in Mid-August 2016, weather permitting.

Image_95thStWestsideupcoming_June-August_2016-05-04-01

Image_MarshallDrive-95thStreetTrafficFlow_2016-05-04-01

Fall 2015 Project Update 10

Read the latest comprehensive project update summarizing the work completed and some of the upcoming changes.

 

February 2015 Project Update 9

The February 2015 Project Update provides and overview of the current construction and highlights upcoming work for 2015.

This version is best for viewing on the online. This Project Update was formatted as an 11×17 landscape document.

Traffic Alert: K-10 & Ridgeview Road Interchange Overnight Closures

TRAFFIC ALERT

FOR IMMEDIATE RELEASE
February 6, 2015
News Contact: Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

K-10 & Ridgeview Road Interchange

EXPECT DELAYS! WEEKDAY OVERNIGHT LANE – RAMP – ROADWAY CLOSURES: The following overnight lane, ramp and roadway closures will take place at the K-10 and Ridgeview Road interchange for demolition work on the west half of the existing Ridgeview Road bridge over K-10 (which is part of the new diverging diamond interchange work underway) in Johnson County.

Crews will remove the existing bridge, sections at a time, utilizing heavy equipment. Sometime next week between Wednesday-Friday, February 11-13, traffic will be shifted onto the east half of the new Ridgeview Road bridge over K-10.

Eastbound and westbound K-10 traffic will be reduced to one lane each direction and will detour up the exit ramps, straight through the intersection, and back up the entrance ramps at Ridgeview Road. There will be no ramp access for K-10 traffic to Ridgeview Road or Ridgeview Road traffic to K-10 during the overnight closures. K-10 traffic wishing to access Ridgeview Road will need to utilize the Woodland Road or Renner Boulevard exits on K-10 during the overnight closures.

Ridgeview Road will be closed just closed north of the 105th Street intersection. Ridgeview Road traffic wishing to access K-10 must use the Woodland Road or Renner Boulevard interchanges on K-10 during the overnight roadway closure. Access will be provided to the local businesses south of K-10 via the 105th Street intersection. See maps below for lane, ramp and roadway closure locations.

CLOSES at 10:00 p.m. Friday, February 13 – REOPENS at 7:00 a.m. Saturday, February 14
• Eastbound and westbound K-10 left lanes under Ridgeview Road CLOSED
• Northbound and southbound Ridgeview Road from 105th Street north to K-10 CLOSED

CLOSES at 8:00 p.m. Monday, February 16 – REOPENS at 5:00 a.m. Tuesday, February 17
• Eastbound and westbound K-10 left lanes under Ridgeview Road CLOSED
• Northbound and southbound Ridgeview Road from 105th Street north to K-10 CLOSED

CLOSES at 8:00 p.m. Tuesday, February 17 – REOPENS at 5:00 a.m. Wednesday, February 18
• Eastbound and westbound K-10 left lanes under Ridgeview Road CLOSED
• Northbound and southbound Ridgeview Road from 105th Street north to K-10 CLOSED

CLOSES at 8:00 p.m. Wednesday, February 18 – REOPENS at 5:00 a.m. Thursday, February 19
• Eastbound and westbound K-10 left lanes under Ridgeview Road CLOSED
• Northbound and southbound Ridgeview Road from 105th Street north to K-10 CLOSED

Advance message boards will alert traffic to the lane, ramp and roadway closures. Traffic will be directed through the project work zone via signage and cones. Drivers should expect some delays through the project work zone during the overnight closures.

Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone. (KDOT Project #435-46 KA-1002-06)

________________________________________

K-10 Lane Closure Maps:

Ridgeview Road will be closed for bridge demolition work Ridgeview Road will be closed for bridge demolition work

Access to Ridgeview Road from K-10 will be closed overnight for bridge demolition. Access to Ridgeview Road from K-10 will be closed overnight for bridge demolition.

KC Business Journal Kansas breaks ground on Johnson County Gateway

April  22, 2014

Austin Alonzo, Reporter- Kansas City Business Journal

The Johnson County Gateway project is a massive, multiphase reconstruction that aims to reduce congestion in the area where Interstates 35 and 435 and Kansas Highway 10 come together.

April 23rd, 2014|Categories: Home, News Articles|Tags: , , , , |