Westbound I-435 at I-35 Weekend-Long Full Road Closure

TRAFFIC ALERT

FOR IMMEDIATE RELEASE  

September 8, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

I-35 & I-435 Interchange Weekend-Long Full Road Closures

 

WEEKEND-LONG FULL ROAD CLOSURE:  All lanes of westbound I-435 at I-35 CLOSED for bridge patching work beginning at 10 p.m. on Friday, September 16 and reopening at 5 a.m. on Monday, September 19, weather permitting.

A marked detour will be provided via northbound U.S. 69 to 87th Street exit back onto southbound I-35 to access westbound I-435. See marked detour map below.

Advance message boards will alert drivers to the weekend-long full road and ramp closures. Drivers should expect major delays during the weekend-long closures and must use alternate routes.

 

WEEKEND-LONG RAMP CLOSURE:  Northbound I-35 to westbound I-435 loop ramp CLOSED for bridge patching work beginning at 10 p.m. on Friday, September 16 and reopening at 5 a.m. on Monday, September 19, weather permitting.

A marked detour will be provided via northbound I-35 to 95th Street exit with left turns through Diverging Diamond Interchange back onto southbound I-435 to access the westbound I-435 ramp. See marked detour map below.

map_wbi-435_fullclosure_markeddetourroutes_update_2016-09-08-01

Northbound I-35 at I-435 Interchange Overnight Full Road & Ramp Closure

TRAFFIC ALERT UPDATE *New Detour Map*

FOR IMMEDIATE RELEASE  

July 20, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

WEEKDAY OVERNIGHT FULL ROAD & RAMP CLOSURE: Northbound I-35 at I-435 FULLY CLOSED and the northbound I-35 to westbound I-435 ramp CLOSED overnight for the setting of bridge girders on the eastbound and westbound I-435 mainline bridges beginning at 10 p.m. on Monday, July 25 and reopening at 5 a.m. on Tuesday, July 25, weather permitting. Due to a delayed delivery of the bridge girders, this overnight closure has now been rescheduled for a later date.

Advance message boards will alert drivers to the overnight full road closure. Northbound I-35 traffic will detour via eastbound I-435 to northbound U.S. 69 to access northbound I-35. Northbound I-35 to westbound I-435 ramp traffic will detour via eastbound I-435 to Quivira Road exit to access westbound I-435. See NEW marked detour map below.

Map_35Closure_NorthboundClosureDetour_2015-07-18

Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, take it slow, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.

Overall #JoCoGateway Phase Two Project work is scheduled to be completed in December 2016. (KDOT Project #435-46 KA-1002-06)

Southbound I-35 at I-435 Interchange Overnight Full Road & Ramp Closures

TRAFFIC ALERT

FOR IMMEDIATE RELEASE  

July 20, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

WEEKDAY OVERNIGHT FULL ROAD & RAMP CLOSURES: Southbound I-35 from 87th Street to I-435 FULLY CLOSED to traffic for the setting of bridge girders on the eastbound and westbound I-435 mainline bridges beginning at 10 p.m., Thursday-Friday, July 21-22 and reopening at 5 a.m. Friday-Saturday, July 22-23, weather permitting. Note: Southbound I-35 ONE LEFT LANE from 75th Street to I-435 will be CLOSED from 8 p.m. until the 10 p.m. full overnight closure begins. Due to a delayed delivery of the bridge girders, this overnight closure has now been rescheduled for a later date.

In addition, these ramps will be closed overnight:

  • Southbound I-35 to westbound I-435 ramp
  • 87th Street to southbound I-35 on-ramp
  • 95th Street to southbound I-35 on-ramp
  • Southbound I-35 to 95th Street off-ramp

 

Advance message boards will alert drivers to the overnight full road and ramp closures. Traffic will detour via southbound U.S. 69 to westbound I-435 to access southbound I-35. See marked detour map below.

Map_35Closure_SouthboundClosureDetour_2016-07-15

Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.

Overall #JoCoGateway Phase Two Project work is scheduled to be completed in December 2016. (KDOT Project #435-46 KA-1002-06)

Westbound I-435 to Northbound I-35 Ramp LONG-TERM CLOSURE

TRAFFIC ALERT

FOR IMMEDIATE RELEASE  

May 25, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

Westbound I-435 to Northbound I-35 Ramp Long-Term 60-Day Closure

Map_WBI-435toNBI-35Ramp_FullClosure_SignedDetour_2016-05-24

60-DAY LONG-TERM RAMP CLOSURE: Westbound I-435 to northbound I-35 entrance ramp CLOSED for ramp reconstruction work, 24/7 round the clock, beginning at 5 a.m. on Tuesday, May 31 and reopening sometime on Friday, July 29, weather permitting.

Advance message boards will alert drivers to the long-term ramp closure. Westbound I-435 marked detour via northbound U.S. 69 to access northbound I-35. See marked detour map above.

Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

 

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.