alertJohnson County Gateway Phase 2 Construction is now complete. Be aware of additional lane closures as other construction projects begin.

Long Term Closures

/Long Term Closures
­

Long-Term Closures

All long-term closures on the project have been completed!!!

 

 

 

 

 



 

 

 

 

 

 

Westbound I-435 to Northbound I-35 Ramp LONG-TERM CLOSURE

TRAFFIC ALERT

FOR IMMEDIATE RELEASE  

May 25, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

Westbound I-435 to Northbound I-35 Ramp Long-Term 60-Day Closure

Map_WBI-435toNBI-35Ramp_FullClosure_SignedDetour_2016-05-24

60-DAY LONG-TERM RAMP CLOSURE: Westbound I-435 to northbound I-35 entrance ramp CLOSED for ramp reconstruction work, 24/7 round the clock, beginning at 5 a.m. on Tuesday, May 31 and reopening sometime on Friday, July 29, weather permitting.

Advance message boards will alert drivers to the long-term ramp closure. Westbound I-435 marked detour via northbound U.S. 69 to access northbound I-35. See marked detour map above.

Updated daily traffic information for the #jocogateway interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

 

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.

I-35 & I-435 Interchange Long-Term Dual Loop Ramp Closures

FOR IMMEDIATE RELEASE  

April 4, 2016

News Contact:  Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

Map_NBI-35toWBI-435ramp_SBI-35toEBI-435ramp_Detour_FullClosures_2016-03-23-01

I-35 & I-435 Interchange Long-Term Dual Loop Ramp Closures

 

24/7 LONG-TERM DUAL LOOP RAMP CLOSURES: Northbound I-35 to westbound I-435 loop ramp will be CLOSED for pavement reconstruction and tie-in work, 24/7 round the clock, beginning at 10 p.m. on Sunday, April 10 through mid-June 2016, weather permitting. Then the southbound I-35 to eastbound I-435 loop ramp will be CLOSED for the same work, 24/7 round the clock, beginning at 10 p.m. on Monday, April 11 through late October 2016, weather permitting.

NEW CLOSURE! OVERNIGHT ONLY RAMP CLOSURE: Lackman Road to eastbound I-435 ramp will be CLOSED for pavement marking work due to traffic shift for above ramp closures beginning at 8 p.m. on Monday, April 11 and reopening to all traffic at 5 a.m. on Tuesday, April 12, weather permitting. Marked detour will be provided. Lackman Road traffic will detour via southbound Lackman Road to eastbound College Boulevard to northbound Quivira Road or northbound Lackman Road to westbound 95th Street to northbound Renner Boulevard to access eastbound I-435.

NEW CLOSURE! OVERNIGHT ONLY RAMP CLOSURE: Northbound I-35 to eastbound I-435 ramp will be CLOSED for pavement marking work due to traffic shift for above ramp closures beginning at 10 p.m. on Monday-Tuesday, April 11-12 and reopening to all traffic at 5 a.m. on Tuesday-Wednesday, April 12-13, weather permitting (second night is only if needed). Marked detour will be provided. Northbound I-35 traffic will detour via eastbound 87th Street to southbound U.S. 69 to access eastbound I-435.

Advance message boards will alert drivers to the ramp closures. Drivers should expect major delays during peak commute times and must use alternate routes throughout the project duration. Marked detours will be provided as follows. See marked detour map above.

NB I-35 to WB I-435 ramp traffic to detour via eastbound 87th Street to southbound U.S. 69 to westbound I-435. U-Turns are NOT permitted on 87th Street.

SB I-35 to EB I-435 ramp traffic to detour via southbound I-35 to southbound U.S. 69 to eastbound I-435 or via eastbound 119th Street northbound I-35 to eastbound I-435. We recommend that drivers use the detour route via southbound U.S. 69, and NOT the eastbound 119th Street route. The eastbound 119th Street detour route is provided as a backup marked detour route for those drivers who miss the southbound U.S. 69 detour route.

Updated daily traffic information for this interchange project can be viewed at: www.jocogateway.com and for the entire Kansas City Metro Area at: www.ksdot.org/kcmetro/laneclose.asp.

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone.

 

Pflumm Road Under I-35 Bridges

 

Pflumm Road Under I-35 Bridges

24/7 FULL ROADWAY CLOSURE: Northbound and southbound Pflumm Road under the I-35 bridges between Lenexa Drive (on the south) and Marshall Drive (on the north will be FULLY CLOSED to all traffic, 24/7 round the clock, for I-35 roadway reconstruction and bridge widening work beginning sometime the week of May 18 through early October 2015, weather permitting.

There will be NO ACCESS to Pflumm Road traffic between Lenexa Drive and Marshall Drive. A marked detour will be provided. Pflumm Road traffic will detour via 103rd Street to Quivira Road to 95th Street.

Advance message boards will alert drivers to the roadway closure. Traffic will be directed via signage, cones and barricades. Drivers should expect delays and must use alternate routes during the roadway closure.

 

Lenexa Drive at Pflumm Road

>> SPECIAL NOTE: >> UPCOMING 24/7 FULL ROADWAY CLOSURE: Lenexa Drive from Pflumm Road to 102nd Street (as shown on the map above)will be FULLY CLOSED to all traffic for I-35 roadway reconstruction work, 24/7 round the clock, for approximately seven weeks beginning sometime in June 2015, weather permitting. Since these two closures will be occurring simultaneously for a seven-week period, we wanted to provide motorists with the detour routes for both full roadway closures. Advance notification will be sent out once the Lenexa Drive closure date is confirmed.

A marked detour will be provided. Lenexa Drive traffic will detour via 103rd Street to Rosehill Road to 99th Street.

Advance message boards will alert drivers to the roadway closure. Traffic will be directed via signage, cones and barricades. Drivers should expect delays and must use alternate routes during the roadway closure.

PflummRoadandLenexaDr_0515 PflummRoadandLenexaDr_0515

Traffic Alert: Renner Boulevard and Renner Boulevard Ramps Long Term Closure

FOR IMMEDIATE RELEASE

April 8, 2015

News Contact: Kimberly Qualls, (785) 640-9340 or kqualls@ksdot.org

Renner Boulevard & K-10 Interchange

EXPECT DELAYS! 24/7 ROAD & RAMP CLOSURES: All lanes of Renner Boulevard at K-10, eastbound K-10 to Renner Boulevard exit ramp and Renner Boulevard to eastbound K-10 entrance ramp will be CLOSED to all traffic, 24/7 round the clock, beginning sometime Tuesday, April 14, weather permitting. Renner Boulevard is scheduled to reopen in mid-September 2015, and the eastbound K-10 Renner Boulevard ramps are scheduled to reopen in August 2015, weather permitting.

These closures are needed as crews will completely reconstruct the interchange ramps, as well as reconstruct Renner Boulevard south of K-10 due to a significant roadway grade change in this area.

SPECIAL NOTE: > > Renner Boulevard and the adjacent K-10 ramps will FULLY CLOSE once College Boulevard is opened to four-lanes of traffic which is planned for some time during the day this Tuesday, April 14, weather permitting. Renner Boulevard at K-10 cannot fully close until College Boulevard is fully opened to four lanes of traffic.

Advance message boards will alert traffic to the ramp and roadway closures. Marked detours will be provided. See the three detour maps below for Renner Boulevard through traffic detour; Renner Boulevard to K-10/I-435 detour; and K-10/I-435 to Renner Boulevard detour.

Traffic will be directed through the project work zone via signage and cones. Drivers should expect delays and must use alternate routes during these long-term closures.

Updated daily traffic information for the #jocogateway interchange project can be viewed at www.jocogateway.com and for the entire Kansas City Metro Area at www.ksdot.org/kcmetro/laneclose.asp.

The Kansas Department of Transportation urges all motorists to be alert, obey the warning signs, and “Give ‘Em a Brake!” when approaching and driving through the project work zone. The overall #jocogateway project is scheduled to be completed in late December 2016. (KDOT Project #435-46 KA-1002-06)

Marked detour routes are as follows:

Renner3

 

Renner2Renner1